RAWI member Sarens performed installation of 3 Enercon E-70 near Kaliningrad, Russia


Share this post

Not far from the village Ushakovo, 20 kilometers from Kaliningrad, Russia, the Sarens (RAWI member) team in March 2018 completed the mechanical installation of three Enercon E-70s with a capacity of 2.3 MW each.

For the installation of these WTG, the Liebherr LTM-1750-9.1 crane with a lifting capacity of 750 tons was used. As a subsidiary crane, a Terex Demag crane with a load capacity of 200 tons was used.

The installation of the turbine was carried out in several stages. First, a base ring with a weight of 17.8 tons. Then electric modules were installed. The following modules, 3 sections with a weight of 54, 38, 42 tons, respectively, were raised and mounted.

After all the sections were installed, a Nacelle weighing 19 tons and a generator weighing 52 tons were mounted at a height of 65 meters. Further on, a rotor with blades was assembled. The length of one such blade is 35 meters. At the final stage, using 2 hooks, a rotor assembly with 51-ton blades was raised and mounted.

The project was carried out in hard weather conditions. The mark of the thermometer often fell below -18, regular winds above 10 m/s.


Share this post